A standard Generac standby generator installation takes one to three days of on-site work from equipment delivery to first operational power, provided permits are already approved and the mounting pad is cured. The electrical portion, which includes transfer switch installation, panel connection, and generator wiring, typically takes four to eight hours for an experienced electrician. The gas line connection adds two to four hours for a licensed plumber or gas fitter.

The total project timeline from order to operational is typically two to four weeks when all pre-installation steps are accounted for. Permit processing takes one to three weeks depending on the municipality. Concrete pad curing requires seven days minimum before placing the generator. Equipment shipping from IB Lighting is nationwide with delivery typically in three to seven business days after order. Ordering the generator while permits are being processed eliminates overlap time and keeps the project on schedule.

A well-coordinated installation sequences the steps so that permits are submitted on the day the order is placed, the pad is poured during the permit processing period, and the generator arrives just as the pad and permits are ready. Our expert support team can help you build this sequence for your project. Contact us or browse our Generac home standby generators. Free Freight Insurance Included.

Expert Source: This answer was prepared by the IB Lighting technical team. For additional guidance specific to your project, call us at (800) 674-9019 or contact us online.